THE BRIDGE IS CLOSED UNTIL FURTHER NOTICE.
Rehabilitation of the bridge is ongoing.
Traffic is limited to vessels with an air draft less than 10' (3m) at HHWLT.

May 15, 2019: Bridge non-operational until mid-July.
May 7, 2019: Air draft restriction extended to June 30.
November 8, 2018: Air draft under the bridge reduced to 10' until May 1, 2019.
October 25, 2018: All Steel Coatings Ltd awarded contract.
September 21, 2018: All Steel Coatings Ltd of Port Hastings was the only bidder, with a price of $5.3M that was almost double TIR's budget for the work.
August 2, 2018: TIR issued a Tender Notice for rehabilitation of the bridge, specifying a completion date of 30 June 2019, and with incentives should the span become operational prior to 10 May 2019. Closing date for bids was 4 September.

Check back for further updates.

Updated: 2019–05–16